I'm attempting to import into Method from an Excel spreadsheet. I downloaded the utility and watched the webinar that Ryan presented. I'm getting an error message that there is an unknown library or catalog. I'm using Windows Vista with Office 2007. When I attempt to install Soap Type Library 3.0 from the Microsoft site I see that ...
-
Steven emailed with the following reply:
OK. I used hourly, thinking I would get an estimated Contract Amount. What's the definition of Charge Qty by the way?
I'm going to start over and use the exact example in the tutorial, since I am really struggling with using my own. Is it necessary to have an Activity ...
-
I am suggesting that the use of projects and phases just stay on the Method side. Right now, if you set up a project in Method it becomes a job on the QuickBooks side.
Unfortunately, we have list limitations in Quickbooks.
If I create a project for my team to work on, I don't want it to show up as a job in ...
-
Hi,
Let’s see if I can help get things moving. When you added the new project what Contact Type did you specify? The example I used in my Tutorial was a Fixed contract. If I were to use Hourly as an example, it would not update the Contact Amount because it’s unlikely there was actual time / Charge Qty entered at the time the ...
-
calendar is fine as of 11am . thanks for the fast service!!!!
-
I'm afraid I am off to a bad start with this Beta. I decided to walk through the Tutorial in the Quick Start Guide using as a sample a project I just started working on. I entered a new project in step 2 and input "3" as an Est Qty, $75 as a rate, and when I clicked "Update" nothing happened. ...
-
Richard -
Can you check now?
I logged in just now and it seemed fine from the Eastern time zone. I also tried logging into a computer on Central time and it seemed fine too.
I think you are on to something with the daylight savings time, though. Perhaps what happened was that the servers are in Central time and ...
-
Hello Richard,
Thank you for pointing this out to us, we are looking into it. It is our top priority and I'll keep you posted.
-
All calendar entries are displaying one hour earlier than time listed on activities, i.e., my scheduled 9Am appt. is showing as a 8am appt.on the calendar.
I think this just started today, without any changes to Method screens, etc.. Well, presumably so, that is!
Tried unchecking DST, logging out, back in. No difference.
-
Ryan,
QB was open during these events, so I'm not sure why it was happening. Especially the invoice that would not ever populate the invoice number or customer info.