Support,
While testing some screen functions, I noticed that I can't back date Actual Completed Date on Activities or Work Orders. I had to edit the Work Order screens to show actual completed date. In some cases, my crews are unable to complete work orders in the field so they will complete them at home. The problem is that when they save and close the work order, it uses the current date/time for the actual completed date and time. For some reason, we can't over ride it. It also happens on the default Activities screen. This wasn't a problem with previous versions of Method.
Again, the work order screen is customized; however, the activities screen is default and they both have the same outcome. Any advice would be appreciated.
Regards,
James Stapleton
1st Rate Pool Service, Inc.
214-985-1883