    Work order date

    In the add edit work order screen is it possible to show the due start date, and end date with no time?

    Only date

  • 05-15-2013 8:41 AM In reply to

    Re: Work order date

    Answer

    Hi Marcelo, 

    Yes, you can customize this. Copy and edit the screen called FieldService_AddEditWorkOrder. In the screen designer, edit the Date Start* and Date End* objects. Skip to Step 4 of 5: Date/Time Formatting and uncheck the four check boxes. See the screenshot below. Let me know if this works for you. 

    Jason

     