    Case Actvity Status History

    A quick question about activities.  Does Method keep a history of the date of status changes in Case Activities?  For example, if we had a phone call regarding a problem that was entered on 3/1/15 with a status of Not Started, updated on 3/2 with a status of In Progress and on 3/3 with a status of Completed, is there any way to view/report on how long it took to go from initial request to completion.

    Thanks as always,

    Mike

  • 03-04-2015 11:11 AM In reply to

    Re: Case Actvity Status History

    Hi techconnect,

    Are you trying to get the Case: Opened > Closed time, or the Activity: Created > Completed time?

    - Justin

    Justin Henderiks
    Technical Sales Specialist
    Method Integration Inc.
    Toll Free: 1.888.925.6238
    Local and overseas: 416.847.0400
    Fax: 416.640.6027
    E-mail: j.henderiks@method.me
  • 03-05-2015 4:53 AM In reply to

    Re: Case Actvity Status History

    Justin,

    It would be the Activity created -> completed time.

    Thanks,

    Mike

  • 03-05-2015 11:22 AM In reply to

    Re: Case Actvity Status History

    Answer

    Hi techconnect,

    There are CreatedDate and CompletedDate fields within the Activity table, so you could build a screen or report to check these values and report on them as you'd like.

    Hope this helps.

    - Justin

    Justin Henderiks
    Technical Sales Specialist
    Method Integration Inc.
    Toll Free: 1.888.925.6238
    Local and overseas: 416.847.0400
    Fax: 416.640.6027
    E-mail: j.henderiks@method.me
Page 1 of 1 (4 items)