Method Community

 

Activity Status

Last post 04-25-2013 9:54 AM by Method_Jason. 1 replies.
Page 1 of 1 (2 items)
Sort Posts: Previous Next
  • 04-25-2013 5:43 AM

    Activity Status

    Can the activity status be changed to something I am more familiar with?, for example:

    not statrted to active

    in progress to on route

    etc.

  • 04-25-2013 9:54 AM In reply to

    Re: Activity Status

    Answer

    Hi Marcelo, 

    If you click the three dots button beside the status field you should be brought to a screen where you can edit and add statuses. See the screenshot below. Hope this helps!

    - Jason 