Good Day!
I am wondering whether I am doing something wrong.
I am creating activities for a future date. The activities have an Activity Status of Not Started. I save the activity. I am not using Save and Complete.
When I look at the activity, it has a completion date and a negative duration.
When I do Save and Complete the activity, the completion date and duration are not updated.
If the activity is Not Started, shouldn't the completion date be blank and the duration also be blank (zero)?
When the activity is completed, shouldn't the completion date and duration be updated?
Jim